SCHEDULER DEMO


Trying a random permutation placed the jobs in the order green, purple blue and brown generating a total sum of weighted completion time to be 119.8

Using the Weighted Shortest processing time algorithm however as you can see generated a total sum of weighted completion time of 110.6 (which is of course a better solution!)

Name length weight
Job 1 (blue) 2 2
Job 2 (brown) 3 3
Job 3 (purple) 1.2 4
Job 4 (green) 5 9