SCHEDULER DEMO


Now lets try a different scenario. This has 4 jobs with no ready times, due dates or precedence constraints. Suppose we need to find the minimum weighted sum of completion times.

Name length weight
Job 1 (blue) 2 2
Job 2 (brown) 3 3
Job 3 (purple) 1.2 4
Job 4 (green) 5 9