SCHEDULER DEMO


Weighted Shortest Processing Time gives us a total tardiness of 7.56 units which turns out to be slightly better than the random permutation.

Next let's try sorting by earliest due date.



Name length readytime due date Weight
Job 1 1 1.4 9.48 4
Job 2 3.4 2 9 4
Job 3 3.88 2 6 3
Job 4 5 5 11 4
Job 5 5 3 10 1